Last steps before the Genius CAB is finished

 

CCC - Cab Concept Cluster
Construction of the Genius CABs began in January 2016 in the assembly halls at Fritzmeier.
In the scope of a unique cooperative venture among the individual cluster partners,
all nine Genius CABs were assembled and went into operation in less than ten weeks.
During these ten weeks, coordination meetings took place almost on a weekly basis in subproject groups.
Optimization of individual components, such as software updates or short-term adaptations
and changes went hand in hand and, just like during the development stage, communication
among cluster partners was excellent despite the approaching deadline.

https://www.youtube.com/watch?v=cmpX9QkVv20

Last steps before the Genius CAB is finished